Case Study: Cardinal Health
Project Scope: Cable new three story building, including:
Project Scope: Cable new three story building, including:
- Cable approximately 2250 workstations and offices
- Design and build Server room
- Design and build IDF Rooms
Schedule: 1st & 2nd Floor completed in 10 weeks, 3rd Floor completed in 10 weeks.
Critical Business Issue:
- 1st & 2nd Floor Rough-In (Approximately 2100 cables) had to be installed within 3 weeks to coordinate with ceiling installation.
- 3rd Floor Rough-In (Approximately 2400 Cables) within 4 weeks to allow warehouse racking and shelving installation. Missed deadline would not allow future access to floor cores for modular furniture cabling.
- Large percentages of cables were going to be out of TIA/EIA-568-B.1 horizontal cabling specifications due to deficiencies in architectural engineering.
Capabilities:
- BICSI ANSI/TIA/EIA Compliance Review
- Project Management
- Data Center Design
- Horizontal Cabling
Results:
- Completed all phases on-time, within budget.
- All cables in ANSI/TIA/EIA compliance
Services include...
• Horizontal Structured Cabling
• Riser cabling
• Data Center Design
• Fiber Optic cabling
• Cross Connect Wiring
• Patch Cord Installation
• TIA/EIA Compliance
• Sound Masking
• Horizontal Structured Cabling
• Riser cabling
• Data Center Design
• Fiber Optic cabling
• Cross Connect Wiring
• Patch Cord Installation
• TIA/EIA Compliance
• Sound Masking
Case studies...
We've helped our Customers with their Cable & Fiber, and we'd like to share with you how.
• Cardinal Health
• USA Federal Credit Union
• L-3 Communications
Frequently asked...
Click here to read the questions we hear most about Cable & Fiber.
Looking for an answer you can't find? Send us an email.