Case Study: Cardinal Health
 
cable toolProject Scope: Cable new three story building, including:
  • Cable approximately 2250 workstations and offices
  • Design and build Server room
  • Design and build IDF Rooms

Schedule: 1st & 2nd Floor completed in 10 weeks, 3rd Floor completed in 10 weeks.
 
Critical Business Issue: 

  • 1st & 2nd Floor Rough-In (Approximately 2100 cables) had to be installed within 3 weeks to coordinate with ceiling installation.
  • 3rd Floor Rough-In (Approximately 2400 Cables) within 4 weeks to allow warehouse racking and shelving installation. Missed deadline would not allow future access to floor cores for modular furniture cabling.
  • Large percentages of cables were going to be out of TIA/EIA-568-B.1 horizontal cabling specifications due to deficiencies in architectural engineering.

Capabilities:

  • BICSI ANSI/TIA/EIA Compliance Review
  • Project Management
  • Data Center Design
  • Horizontal Cabling

Results:

  • Completed all phases on-time, within budget.
  • All cables in ANSI/TIA/EIA compliance



Services include...
• Horizontal Structured Cabling
• Riser cabling
• Data Center Design
• Fiber Optic cabling
• Cross Connect Wiring
• Patch Cord Installation
• TIA/EIA Compliance
• Sound Masking

Case studies...
We've helped our Customers with their Cable & Fiber, and we'd like to share with you how.

Cardinal Health
USA Federal Credit Union
L-3 Communications

Frequently asked...
Click here to read the questions we hear most about Cable & Fiber.

Looking for an answer you can't find? Send us an email.